Công trình công cộngCâu 1602 / 1605
When calculating whether it has met the prevailing wage obligation, a contractor may generally credit:
a.Employer payments for bona fide fringe benefits (health, pension, vacation, training) toward the total prevailing wage obligation
b.The contractor's overhead
c.Meals provided to workers
d.Only cash paid, never benefits
Giải thích
Labor Code §1773.1 lets employers count qualifying fringe benefit contributions (health/welfare, pension, vacation/holiday, apprenticeship training) toward the total prevailing wage obligation. The worker must still receive at least the required total of cash wage plus creditable benefits.
Trích dẫn luật: Labor Code §1773.1Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- The performance bond on a public works project protects the:
- DIR public works contractor registration generally must be:
- A subcontractor on a public works project is not paid. To make a claim on the prime contractor's payment bond, the subcontractor generally must:
- On a public works project, the prevailing wage obligation applies to:
- The main reason competitive sealed bidding is used for public works is to:
- A public agency may reject all bids on a public works project when:
Cập nhật gần nhất: · quy trình kiểm tra
Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)