On a public works project, the prevailing wage obligation applies to:
a.Only those workers who ask to be paid the prevailing rate
b.Only the workers dispatched from a union hiring hall
c.All workers in covered crafts, subs' included
d.Only the prime contractor's own payroll employees
Giải thích
Labor Code §1774 binds the contractor and every subcontractor to pay not less than the prevailing rate, and §1772 covers all workers employed on the public work in covered classifications. The duty is not waivable by silence, so a worker who never asks is still owed it. Union membership and dispatch are irrelevant: the rate is set by craft and county, not by who hired the worker. Confining it to the prime's own payroll is the error §1774 exists to prevent, since most public works labour is performed by subcontractors.
Trích dẫn luật: Labor Code §1774; §1772Luyện miễn phí toàn bộ 1632 câu hỏi — không cần đăng ký.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Câu hỏi liên quan cùng chủ đề
- DIR public works contractor registration generally must be:
- A subcontractor on a public works project is not paid. To make a claim on the prime contractor's payment bond, the subcontractor generally must:
- When calculating whether it has met the prevailing wage obligation, a contractor may generally credit:
- The main reason competitive sealed bidding is used for public works is to:
- A public agency may reject all bids on a public works project when:
- A subcontractor on a DIR-monitored public works job furnishes no certified payroll for 62 days past the first deadline, then uploads everything at once. What does Labor Code §1771.4 authorize, and where should those records have gone?
Cập nhật gần nhất: · quy trình kiểm tra
Đội ngũ PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)