A claimant recorded a mechanics lien and did nothing further for four months. What is the status of the lien?
Giải thích
Civil Code §8460(a) requires the claimant to commence an action to enforce the lien within 90 days after the claim of lien is recorded, and provides that the lien otherwise expires and is unenforceable; four months is past the deadline. (c) uses a real figure from the wrong subdivision: §8460(b) extends the deadline only where the claimant and owner agreed to extend credit and recorded notice of it, and even then no later than one year after completion. (a) and (d) invent conversions the statute does not provide — a judgment lien needs a judgment, and a stop payment notice is a separate remedy that must be given while undisbursed funds remain.
Trích dẫn luật: Civ. Code §8460(a)-(b)Luyện miễn phí toàn bộ 1632 câu hỏi — không cần đăng ký.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Câu hỏi liên quan cùng chủ đề
- A performance bond on a construction project primarily guarantees to the obligee that:
- Which of the following is generally NOT covered by a standard Commercial General Liability policy?
- Commercial auto insurance for a contractor is primarily intended to cover:
- A subcontractor recorded a mechanics lien but never served a copy on the owner and did not attach a proof of service affidavit. The likely result is:
- A subcontractor asks to be added as an 'additional insured' on the general contractor's CGL policy. From a risk-management standpoint, this request is:
- Which best describes who must carry workers' compensation insurance?
Cập nhật gần nhất: · quy trình kiểm tra