On a private project financed by a construction lender, a subcontractor who fails to serve the preliminary notice on the LENDER primarily loses the ability to:

a.Reach the construction loan funds via a stop payment notice against the lender
b.Collect workers' compensation
c.Record any lien at all
d.Sue the subcontractor's own customer

Giải thích

Serving the construction lender preserves the ability to use a bonded stop payment notice to reach undisbursed loan funds. Failing to notify the lender undercuts that fund-based remedy, though other remedies against the owner's property may remain if the owner was properly noticed.

Trích dẫn luật: Civ. Code §8410