A contractor who records a mechanics lien for an amount it knows is willfully overstated risks:

a.Nothing, because the court simply reduces the lien to the correct sum
b.A recording fee penalty only, with the lien enforceable as corrected
c.Losing the entire lien and being liable to the owner for damages
d.Having the lien reduced and the excess added to the payment bond claim

Giải thích

Civil Code §8422 makes a claim of lien void to the extent it includes work not provided or is willfully overstated, and the claimant can lose the lien altogether and face liability for the owner's resulting damages. (a) is the widespread and costly assumption that padding is free because a judge will simply trim it. (b) treats the consequence as a fee. (d) invents a transfer between remedies — overstating a lien does not move the surplus onto a bond, and a willfully false bond claim carries its own exposure.

Trích dẫn luật: Civil Code §8422

Luyện miễn phí toàn bộ 1632 câu hỏi — không cần đăng ký.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Câu hỏi liên quan cùng chủ đề

Cập nhật gần nhất: · quy trình kiểm tra

Đội ngũ PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)
Báo lỗi