A preliminary notice must be given by which method to be effective?
Giải thích
Civil Code §8106 allows notice under this part by personal delivery, by mail in the manner §8110 prescribes, or by leaving the notice and mailing a copy as Code of Civil Procedure §415.20 provides; §8110 defines that mail as registered or certified mail, express mail, or overnight delivery by an express service carrier, and §8118 governs proof of notice. (a) confuses service with recording: the preliminary notice is served on the owner, direct contractor, and lender, while the claim of lien is what gets recorded. (b) is a substituted-service device this part does not use. (d) is outside the permitted means no matter what receipt the sender keeps.
Trích dẫn luật: Civ. Code §8106 / §8110 / §8118Luyện miễn phí toàn bộ 1632 câu hỏi — không cần đăng ký.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Câu hỏi liên quan cùng chủ đề
- A contractor who records a mechanics lien for an amount it knows is willfully overstated risks:
- Separate from project insurance, the CSLB requires every active licensed contractor to maintain a 'contractor's bond' (contractor license bond). Its main purpose is to:
- Which statement about the CSLB license bond and a project performance bond is TRUE?
- A subcontractor's certificate of insurance names the general contractor as 'certificate holder.' Being a certificate holder means the general contractor:
- On a private work of improvement where a valid payment bond has been recorded, an unpaid subcontractor may:
- A notice of cessation was recorded after a 30-day work stoppage. This recording affects lien deadlines by:
Cập nhật gần nhất: · quy trình kiểm tra