On a private work of improvement where a valid payment bond has been recorded, an unpaid subcontractor may:
Giải thích
A private-work payment bond adds a surety to pursue; it does not by itself extinguish lien rights, and a claimant may hold both remedies while recovering the debt only once. The real qualification is Civil Code §8600: where the owner in good faith files the direct contract with the county recorder and records a payment bond of at least 50 percent of the contract price before work commences, the court shall, where equitable, restrict lien enforcement to the bond. (a) states that outcome as though it were automatic, which it is not. (b) is double recovery, which no remedy permits. (d) misreads who may claim on the bond: §8608 gives the right to claimants who provided work to the direct contractor, directly or through subcontractors.
Trích dẫn luật: Civ. Code §8600 / §8608Luyện miễn phí toàn bộ 1632 câu hỏi — không cần đăng ký.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Câu hỏi liên quan cùng chủ đề
- Which statement about the CSLB license bond and a project performance bond is TRUE?
- A preliminary notice must be given by which method to be effective?
- A subcontractor's certificate of insurance names the general contractor as 'certificate holder.' Being a certificate holder means the general contractor:
- A notice of cessation was recorded after a 30-day work stoppage. This recording affects lien deadlines by:
- 'Completed operations' coverage under a CGL policy is important to contractors because it covers:
- A sole-owner contractor holding only a Class B license, with no employees, wants to avoid carrying workers' compensation. Under B&P §7125 as it reads until January 1, 2028, the contractor may:
Cập nhật gần nhất: · quy trình kiểm tra