A notice of cessation was recorded after a 30-day work stoppage. This recording affects lien deadlines by:

a.Triggering 30 days for other claimants and 60 days for the direct contractor
b.Triggering 60 days for other claimants and 90 days for the direct contractor
c.Leaving every claimant with 90 days from actual completion of the work
d.Extending each claimant's deadline to one year from the recording date

Giải thích

A recorded notice of cessation has the same effect as a notice of completion: Civil Code §8414 cuts claimants other than the direct contractor to 30 days after recording, and §8412 gives the direct contractor 60 days. (b) swaps the two figures, and reversing them is the most common error on this pair. (c) is the rule when nothing is recorded — 90 days after completion for everyone — and is exactly what the recording is meant to shorten. (d) confuses this with the §8460 outer limit for bringing a foreclosure action after a lien is recorded.

Trích dẫn luật: Civil Code §8412 / §8414

Luyện miễn phí toàn bộ 1632 câu hỏi — không cần đăng ký.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Câu hỏi liên quan cùng chủ đề

Cập nhật gần nhất: · quy trình kiểm tra

Đội ngũ PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)
Báo lỗi