Bảo hiểm & Quyền cầm giữCâu 1535 / 1605
A notice of cessation was recorded after a 30-day work stoppage. This recording affects lien deadlines by:
a.Triggering the shorter deadlines: 30 days for other claimants and 60 days for the direct contractor
b.Having no effect on deadlines
c.Eliminating the direct contractor's lien rights
d.Extending all deadlines to one year
Giải thích
A recorded notice of cessation (like a notice of completion) triggers the shorter statutory deadlines under Civil Code §8414: 30 days for claimants other than the direct contractor, and 60 days for the direct contractor. Without it, all have 90 days from completion.
Trích dẫn luật: Civ. Code §8414Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- A preliminary notice in California must be served by which method to be effective?
- A subcontractor's certificate of insurance names the general contractor as 'certificate holder.' Being a certificate holder means the general contractor:
- On a private work of improvement, when a valid payment bond has been recorded, an unpaid subcontractor may:
- 'Completed operations' coverage under a CGL policy is important to contractors because it covers:
- A sole-owner contractor with no employees wants to avoid carrying workers' compensation insurance. Generally, the contractor may:
- To keep a mechanics lien alive beyond 90 days without immediately filing suit, a claimant and owner may agree to and record an:
Cập nhật gần nhất: · quy trình kiểm tra
Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)