To keep a mechanics lien alive beyond 90 days without immediately filing suit, a claimant and owner may agree to and record an:

a.Assignment of the lien to the construction lender holding the loan
b.Extension of credit, extending time to sue up to a year
c.Amendment increasing the lien to include interest accruing meanwhile
d.Acknowledgement of debt, which restarts the 90 days from signing

Giải thích

Civil Code §8460 requires an action to enforce a lien within 90 days after recording, unless a notice of credit is recorded extending the time — and in no event may the action be brought more than one year after recording. (a) transfers the claim without touching the deadline; an assignee inherits the same clock. (c) confuses the amount with the time limit, and inflating a lien invites the §8422 overstatement problem. (d) imports a debt-acknowledgement rule from the statute of limitations, which does not restart the mechanics lien deadline.

Trích dẫn luật: Civil Code §8460

Luyện miễn phí toàn bộ 1632 câu hỏi — không cần đăng ký.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Câu hỏi liên quan cùng chủ đề

Cập nhật gần nhất: · quy trình kiểm tra

Đội ngũ PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)
Báo lỗi