Bảo hiểm & Quyền cầm giữCâu 1472 / 1605
Which type of claimant is generally NOT required to serve a Preliminary Notice to preserve a mechanics lien?
a.A material supplier to a subcontractor
b.A sub-subcontractor
c.An equipment rental company renting to a subcontractor
d.A laborer performing work for wages (as to lien rights for wages)
Giải thích
Under Civil Code §8200(e), a laborer (as to wages) is excused from serving a preliminary notice. Most others without a direct owner contract — subs, material suppliers, equipment lessors — must serve the preliminary notice to preserve lien and stop payment notice rights.
Trích dẫn luật: Civ. Code §8200Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- After a Notice of Completion is recorded on a private work of improvement, the DIRECT (prime) contractor must record its mechanics lien within:
- The California 'Preliminary Notice' (often called the 20-day notice) must generally be served within 20 days after the claimant first furnishes labor or materials. What is the primary consequence of serving it late?
- On a private project, a subcontractor who has no direct contract with the owner must serve a Preliminary Notice on which parties to preserve mechanics lien rights?
- A direct contractor who contracted directly with the owner on a private residential project generally must serve a preliminary notice on which party, if any?
- To remove a recorded mechanics lien from the property when a payment dispute is resolved, the contractor typically records a:
- After recording a mechanics lien, within what period must the claimant file a lawsuit (action) to foreclose the lien, or the lien becomes unenforceable?
Cập nhật gần nhất: · quy trình kiểm tra
Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)