A direct contractor who contracted directly with the owner on a private residential project generally must serve a preliminary notice on which party, if any?

a.On every subcontractor and supplier working under the prime contract
b.On the owner, within 20 days, to preserve any lien right
c.On no one, because a direct contract dispenses with all notice
d.On the construction lender only, if the project has one

Giải thích

Civil Code §8200(e) excuses a direct contractor from serving the owner — the contract itself gives the owner notice — but the direct contractor must still give the preliminary notice to a construction lender to preserve rights against the construction funds. (a) inverts the flow: notice runs up the chain toward the people who control the money, not down it. (b) applies the general rule without reading the exception, and is the trap for anyone who memorised '20 days' alone. (c) over-reads the exception, which covers only the owner and not the lender.

Trích dẫn luật: Civil Code §8200(e)

Luyện miễn phí toàn bộ 1632 câu hỏi — không cần đăng ký.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Câu hỏi liên quan cùng chủ đề

Cập nhật gần nhất: · quy trình kiểm tra

Đội ngũ PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)
Báo lỗi