Bảo hiểm & Quyền cầm giữCâu 1473 / 1605
A direct contractor who contracted directly with the owner on a private residential project generally must serve a preliminary notice on which party, if any?
a.On every subcontractor on the job
b.On the owner, within 20 days, to preserve any lien right
c.On the CSLB registrar
d.Only on a construction lender, if one exists; a preliminary notice is otherwise not required to the owner because of the direct contract
Giải thích
A direct contractor with a contract with the owner need not serve the owner a preliminary notice, but under Civil Code §8200 must give notice to a construction lender (if any) to preserve rights against construction funds. The direct owner contract itself satisfies the notice purpose as to the owner.
Trích dẫn luật: Civ. Code §8410Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- The California 'Preliminary Notice' (often called the 20-day notice) must generally be served within 20 days after the claimant first furnishes labor or materials. What is the primary consequence of serving it late?
- On a private project, a subcontractor who has no direct contract with the owner must serve a Preliminary Notice on which parties to preserve mechanics lien rights?
- Which type of claimant is generally NOT required to serve a Preliminary Notice to preserve a mechanics lien?
- To remove a recorded mechanics lien from the property when a payment dispute is resolved, the contractor typically records a:
- After recording a mechanics lien, within what period must the claimant file a lawsuit (action) to foreclose the lien, or the lien becomes unenforceable?
- A 'stop payment notice' (formerly 'stop notice') is a remedy that allows an unpaid claimant to reach:
Cập nhật gần nhất: · quy trình kiểm tra
Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)