A direct contractor who contracted directly with the owner on a private residential project generally must serve a preliminary notice on which party, if any?

a.On every subcontractor on the job
b.On the owner, within 20 days, to preserve any lien right
c.On the CSLB registrar
d.Only on a construction lender, if one exists; a preliminary notice is otherwise not required to the owner because of the direct contract

Giải thích

A direct contractor with a contract with the owner need not serve the owner a preliminary notice, but under Civil Code §8200 must give notice to a construction lender (if any) to preserve rights against construction funds. The direct owner contract itself satisfies the notice purpose as to the owner.

Trích dẫn luật: Civ. Code §8410

Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.

Câu hỏi liên quan cùng chủ đề

Cập nhật gần nhất: · quy trình kiểm tra

Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen Licensed California General Contractor (CSLB License #1101856 kiểm tra)
Báo lỗi