Công trình công cộngCâu 1626 / 1632
On a public work, a contractor lets three laborers work 10 hours a day for four days and pays straight time throughout. Under Labor Code §1813, what does the contractor forfeit, over and above the overtime it still owes?
a.$100, being $25 for each of the four days on which the crew worked past eight hours
b.$600, being $25 for each of the 24 overtime hours the three laborers logged that week
c.$2,400, being $200 for each worker for each day, the penalty for a prevailing wage shortfall
d.$300, being $25 for each worker for each calendar day on which the violation occurred
Giải thích
Section 1813 forfeits $25 for EACH WORKER for EACH CALENDAR DAY on which that worker is required or permitted to work more than 8 hours in a day or 40 hours in a week without the overtime pay §1815 requires. Three workers across four days is twelve worker-days, and twelve times $25 is $300. The forfeiture is counted per worker per day, not per day and not per overtime hour, and it is separate from the wages still owed. The $200 figure is the ceiling in §1775 for underpaying the prevailing wage, which is a different violation.
Trích dẫn luật: Labor Code §1813; §1775(a)(1)Luyện miễn phí toàn bộ 1632 câu hỏi — không cần đăng ký.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Câu hỏi liên quan cùng chủ đề
- On a public works project, the prevailing wage obligation applies to:
- The main reason competitive sealed bidding is used for public works is to:
- A public agency may reject all bids on a public works project when:
- A subcontractor on a DIR-monitored public works job furnishes no certified payroll for 62 days past the first deadline, then uploads everything at once. What does Labor Code §1771.4 authorize, and where should those records have gone?
- A city awards a $180,000 paving contract. Because the city's land cannot be liened, the prime must post security that unpaid workers, subcontractors and suppliers can reach. What must it furnish, and from whom?
- An unpaid supplier on a school district job learns that the district recorded a notice of completion on April 10. By when must the stop payment notice be given, and what must the district do when it arrives?
Cập nhật gần nhất: · quy trình kiểm tra
Đội ngũ PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)