A 'scope of work' provision in a construction contract is important primarily because it:

a.Defines what work is and is not included in the price
b.Fixes the sequence and duration of each activity on the job
c.Sets how extras will be priced once the owner requests them
d.Transfers to the owner the risk of unknown site conditions

Giải thích

The scope of work fixes the boundary of what the contractor promised: inside it, the work is covered by the contract price; outside it, the work is a compensable extra. Every extras and change-order dispute is decided by reading it, which is why B&P §7159(d)(7) makes a description of the project and the significant materials a required term of a home improvement contract. (b) describes the project schedule, a different document — the scope says what, not when. (c) describes the changes clause, which sets the pricing mechanism once work outside the scope is ordered; the scope only tells you the work IS outside. (d) describes a differing-site-conditions clause; a bare scope statement allocates no risk.

Luyện miễn phí toàn bộ 1632 câu hỏi — không cần đăng ký.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Câu hỏi liên quan cùng chủ đề

Cập nhật gần nhất: · quy trình kiểm tra

Đội ngũ PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)
Báo lỗi