Hợp đồng & Thực hiệnCâu 884 / 1605
A 'severability' (savings) clause provides that if one provision of the contract is found invalid:
a.The price is automatically reduced by half
b.The entire contract is automatically void
c.The remaining valid provisions continue in effect
d.The invalid provision is enforced anyway
Giải thích
A severability clause states that if a court finds one provision invalid or unenforceable, that provision is severed and the remaining valid provisions continue in full effect, preserving as much of the parties' bargain as possible. It prevents a single defective clause from destroying the whole agreement. It does not void the entire contract, resurrect the invalid provision, or automatically cut the price; it isolates the unenforceable term.
Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- A 'scope of work' provision in a construction contract is important primarily because it:
- When a contract's documents conflict, an 'order of precedence' clause is used to:
- An 'indemnification' (hold harmless) clause in a construction contract generally requires one party to:
- An 'attorney fees' clause in a contract typically provides that:
- A contractor and owner sign a contract, then later sign a separate written agreement that clearly changes the completion date and adds $6,000 in scope. This later signed agreement is best described as:
- In a T&M contract dispute, the single most important documentation supporting the contractor's invoices is usually:
Cập nhật gần nhất: · quy trình kiểm tra
Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)