In a T&M contract dispute, the single most important documentation supporting the contractor's invoices is usually:

a.A signed liquidated damages clause
b.Photographs of the contractor's vehicles
c.Accurate daily records of labor hours worked and materials used, with supporting receipts
d.A copy of the contractor's license only

Giải thích

Because a time-and-materials contract bills for actual hours and materials, the contractor's ability to justify and collect on invoices depends heavily on accurate, contemporaneous records: daily time sheets of hours worked and detailed material logs backed by receipts. Without such documentation, T&M billings are easily disputed. A license copy, a liquidated damages clause, or vehicle photos do not substantiate the actual labor and material costs charged.

Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.

Câu hỏi liên quan cùng chủ đề

Cập nhật gần nhất: · quy trình kiểm tra

Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen Licensed California General Contractor (CSLB License #1101856 kiểm tra)
Báo lỗi