In a T&M contract dispute, the single most important documentation supporting the contractor's invoices is usually:

a.A signed liquidated damages clause in the agreement
b.Photographs of the contractor's trucks on the site
c.Daily records of labor hours and materials, with receipts
d.A copy of the contractor's active licence, and nothing else

Giải thích

A time-and-materials contract prices the work by inputs, so an invoice is worth exactly what the record behind it is worth: dated daily logs of who worked and for how many hours at which agreed rate, what material arrived, and the supplier invoices proving it. B&P §7159.10(e)(7) shows the same logic in statute for a service-and-repair job estimated on time and materials — the contract must disclose the set rate, the estimated cost of materials, and how time is computed, in quarter hours, half hours or hours. (a) is irrelevant to proving work done; liquidated damages fix the consequence of a breach in advance. (d) proves a precondition to suing at all under B&P §7031, not the amount owed. (b) documents attendance, not hours, rates, or materials.

Trích dẫn luật: Bus. & Prof. Code §7159.10(e)(7); cf. §7031

Luyện miễn phí toàn bộ 1632 câu hỏi — không cần đăng ký.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Câu hỏi liên quan cùng chủ đề

Cập nhật gần nhất: · quy trình kiểm tra

Đội ngũ PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)
Báo lỗi