A key reason a contractor should ensure the person signing a contract has authority to bind the property is that:
Giải thích
Signing the wrong person costs the contractor twice. The contract binds only the party who signed, so a tenant, a property manager or one co-owner acting alone can leave the contractor with no claim against the person who owns the property — and the mechanics lien is no rescue, because Civil Code §8444 lets an owner who did not contract for the work record a signed and verified notice of nonresponsibility and take the fee interest out of reach. For a home improvement contract, B&P §7159(d) requires the writing to be signed by the parties to the contract, so who signs is a compliance question as well as a collection one. (b) is backwards: less certainty about who is bound makes a written scope more necessary, not less. (c) and (d) are invented — public works status turns on public funds and a public awarding body, and no signature sets a price.
Trích dẫn luật: Civil Code §8444; Bus. & Prof. Code §7159(d)Luyện miễn phí toàn bộ 1632 câu hỏi — không cần đăng ký.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Câu hỏi liên quan cùng chủ đề
- A contractor and owner sign a contract, then later sign a separate written agreement that clearly changes the completion date and adds $6,000 in scope. This later signed agreement is best described as:
- In a T&M contract dispute, the single most important documentation supporting the contractor's invoices is usually:
- An owner and contractor dispute whether a certain task was included in the fixed price. The contract's clear, integrated scope of work does not list that task. Under general interpretation principles, the task is most likely:
- Overall, the single most effective way for a contractor to prevent and win contract disputes over scope, extras, and payment is to:
- A remodeler's printed contract for a single-family home carries an arbitration provision in the same 9-point type as the rest of the document, under the heading 'Dispute Resolution', with no separate space for the owner to initial. What does Bus. & Prof. Code §7191 make of it?
- A prime contractor's standard subcontract requires the subcontractor to indemnify the prime against every loss arising on the job, including a loss caused by the prime's own negligence alone. Under Civil Code §2782, that indemnity is:
Cập nhật gần nhất: · quy trình kiểm tra