A contractor and owner sign a contract, then later sign a separate written agreement that clearly changes the completion date and adds $6,000 in scope. This later signed agreement is best described as:

a.A valid written contract modification supported by new consideration (the added scope and price)
b.An unenforceable oral modification
c.A tort claim
d.A violation of the parol evidence rule

Giải thích

A written, signed agreement that changes the completion date and adds new scope for additional payment is a valid modification of the original contract, supported by fresh consideration because both the added work and the added payment are new, bargained-for exchanges. It is written, not an unenforceable oral change, and it is a contract matter, not a tort. The parol evidence rule does not bar it, since that rule addresses prior or contemporaneous statements, not a later signed modification.

Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.

Câu hỏi liên quan cùng chủ đề

Cập nhật gần nhất: · quy trình kiểm tra

Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen Licensed California General Contractor (CSLB License #1101856 kiểm tra)
Báo lỗi