A contractor bills $75,000 on a job. The contract requires 5% retention and the owner also back-charges $1,500 for a utility relocation. How much will the contractor receive on this billing?

a.$71,250
b.$69,750
c.$73,500
d.$66,000

Giải thích

Retention = 5% of $75,000 = $3,750, leaving $71,250. Subtract the $1,500 back-charge: $71,250 - $1,500 = $69,750 (b). Civil Code §8811 caps private-works retention at 5% for contracts entered into on or after January 1, 2026. (a) $71,250 stops after the retention and forgets the back-charge. (c) $73,500 deducts only the back-charge and forgets the retention. (d) $66,000 is the answer under the superseded 10% retention: $75,000 - $7,500 - $1,500.

Luyện miễn phí toàn bộ 1632 câu hỏi — không cần đăng ký.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Câu hỏi liên quan cùng chủ đề

Cập nhật gần nhất: · quy trình kiểm tra

Đội ngũ PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)
Báo lỗi