A contractor's job had estimated direct costs of $40,000 but actual costs of $46,000. If he had bid a fixed price of $50,000, what was his actual gross profit, and how does it compare to the estimate?
a.$6,000 actual, above estimate
b.$10,000 actual, on target
c.$4,000 actual vs. $10,000 estimated - a $6,000 shortfall
d.A $46,000 loss
Giải thích
Estimated gross profit = $50,000 - $40,000 = $10,000. Actual gross profit = $50,000 - $46,000 = $4,000. The $6,000 cost overrun cut profit from $10,000 to $4,000. Job costing exposes such overruns so future bids improve.
Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- A markup that covers BOTH overhead and profit is sometimes called:
- A contractor bills $75,000 on a job. The contract requires 10% retention and the owner also back-charges $1,500 for a utility relocation. How much will the contractor receive on this billing?
- Which is the best reason to separate business and personal bank accounts?
- A contractor pays $1,200/month for general liability insurance and $2,000/month office rent. These are examples of:
- A subcontractor invoices $9,000 including $600 of California sales tax on materials. On a lump-sum construction contract where the sub is the consumer, the sales tax is:
- A contractor's current assets are $90,000 and current liabilities are $120,000. His working capital is:
Cập nhật gần nhất: · quy trình kiểm tra
Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)