A contractor completes a $180,000 contract billed with 10% retention. Two-thirds of the way through he has billed $120,000. How much retention is being held at that point?
a.$108,000
b.$18,000
c.$6,000
d.$12,000
Giải thích
Retention held to date = 10% of amount billed to date = 10% x $120,000 = $12,000. Retention accrues on each progress billing until released at completion.
Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- The main financial risk of taking on a job much larger than a contractor's usual size is:
- A contractor buys $5,000 of materials with terms 1/15, net 45. If he pays on day 12, what does he pay?
- A contractor's gross profit margin has fallen from 30% to 22% over a year. The most useful first step to diagnose why is to:
- Which of the following BEST reduces a contractor's need for outside financing on a project?
- A contractor's estimate omitted the 9% sales tax on $20,000 of materials. How much profit will this error erase if he cannot pass it on?
- A contractor's business is organized as an S corporation. A key financial feature of an S corp is that:
Cập nhật gần nhất: · quy trình kiểm tra
Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)