A contractor completes a $180,000 contract billed with 5% retention. Two-thirds of the way through he has billed $120,000. How much retention is being held at that point?
a.$9,000
b.$114,000
c.$12,000
d.$6,000
Giải thích
Retention held to date = 5% of the amount billed to date = 5% x $120,000 = $6,000 (d); it accrues on each progress billing until released at completion. Civil Code §8811 caps private-works retention at 5% for contracts entered into on or after January 1, 2026. (a) $9,000 applies the correct 5% to the full $180,000 contract instead of the $120,000 billed. (c) $12,000 is 10% of the billed amount, the pre-2026 private-works custom. (b) $114,000 is the amount paid out, not the amount held.
Luyện miễn phí toàn bộ 1632 câu hỏi — không cần đăng ký.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Câu hỏi liên quan cùng chủ đề
- The main financial risk of taking on a job much larger than a contractor's usual size is:
- A contractor buys $5,000 of materials with terms 1/15, net 45. If he pays on day 12, what does he pay?
- A contractor's gross profit margin has fallen from 30% to 22% over a year. The most useful first step to diagnose why is to:
- Which of the following BEST reduces a contractor's need for outside financing on a project?
- A contractor's estimate omitted the 9% sales tax on $20,000 of materials. How much profit will this error erase if he cannot pass it on?
- A contractor's business is organized as an S corporation. A key financial feature of an S corp is that:
Cập nhật gần nhất: · quy trình kiểm tra
Đội ngũ PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)