Which of the following BEST reduces a contractor's need for outside financing on a project?

a.Larger retention withheld by the owner
b.Prompt billing and quick collection
c.Paying suppliers before invoicing the owner
d.A bigger deposit refunded at closeout

Giải thích

Money borrowed is money the contractor did not collect, so billing the moment work is complete and chasing the payment shortens the gap that a line of credit would otherwise fill. Larger retention withholds more of the earned money for longer and increases the need for financing. Paying suppliers ahead of billing moves cash out before it comes in. And refunding a deposit hands back cash the contractor already holds.

Luyện miễn phí toàn bộ 1632 câu hỏi — không cần đăng ký.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Câu hỏi liên quan cùng chủ đề

Cập nhật gần nhất: · quy trình kiểm tra

Đội ngũ PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)
Báo lỗi