Excavated spoil, materials, and equipment must be kept at least how far back from the edge of an excavation?
a.6 inches
b.1 foot
c.4 feet
d.2 feet
Giải thích
Section 1541(j)(2) requires excavated material and equipment to be kept at least 2 feet from the edge, or to be held by retaining devices sufficient to stop it falling or rolling in, or both. The setback is doing two jobs at once, which is why the standard offers the alternative: the spoil can roll in on a worker, and its weight is a surcharge load that helps cause the cave-in in the first place. Six inches and one foot are too close to do either. Four feet is more than the standard asks and is the figure a candidate reaches for by confusing the setback with a sloping offset.
Trích dẫn luật: 8 CCR §1541(j)(2); 29 CFR 1926.651(j)(2)Luyện miễn phí toàn bộ 1632 câu hỏi — không cần đăng ký.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Câu hỏi liên quan cùng chủ đề
- Who must inspect an excavation for hazardous conditions before employees enter and as conditions change?
- For an excavation deeper than 20 feet, protective systems (such as shoring or shielding) must be:
- A trench is 5 feet deep. What means of egress must be provided for workers?
- Before entering a trench more than 4 feet deep where a hazardous atmosphere could exist (e.g., near landfill or sewer), the employer must:
- In the excavation soil classification system, which classification is the most stable?
- For a simple sloping system in Type C soil (and no engineering), the maximum allowable slope is approximately:
Cập nhật gần nhất: · quy trình kiểm tra
Đội ngũ PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)