公共工程第 1583 / 1632 题

The federal 'Miller Act' and its state counterpart 'Little Miller Acts' require, on public construction projects above threshold amounts, that the prime contractor furnish:

a.A builder's risk policy naming the public agency as an insured
b.A lien waiver from the awarding body before final payment
c.Payment and performance bonds from an admitted surety
d.A bid bond in force for the life of the work

解析

The federal Miller Act and the state Little Miller Acts, including Civil Code §9550, require the prime contractor to furnish a payment bond protecting subcontractors and suppliers and, on most projects, a performance bond protecting the public agency. Builder's risk covers physical damage to the work and answers no payment claim. A lien waiver runs from the claimant to the owner; it is not something the public agency issues. The bid bond does its work at award and is discharged once the contract and the required bonds are executed.

法律依据: 40 U.S.C. §3131; Civil Code §9550

免费刷完整 1632 道题库 — 无需注册。

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

同考点相关题目

最近核对: · 审核流程

PrepPass 团队 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — 核实)
反馈