公共工程第 1585 / 1605 题
A contractor who pays workers LESS than the required prevailing wage on a public works project is subject to:
a.No consequence if the workers agree
b.Automatic loss of the contractor's home
c.Payment of back wages plus statutory penalties per worker per day of violation
d.A warning letter only
解析
Labor Code §1775 requires the contractor to pay the difference (back wages) to underpaid workers and imposes civil penalties for each calendar day each worker was paid less than the prevailing rate. Willful violations increase the penalties. Enforcement is by the Labor Commissioner.
法律依据: Labor Code §1775免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- Because public property generally cannot be subjected to a mechanics lien, unpaid subcontractors on a California public works project are protected primarily by:
- The federal 'Miller Act' and its state counterpart 'Little Miller Acts' require, on public construction projects above threshold amounts, that the prime contractor furnish:
- Competitive bidding on public works generally requires the public agency to award the contract to the:
- Which of the following is the BEST definition of 'public works' for prevailing wage purposes?
- Certified payroll records on a California public works project must generally be made available for inspection and, when requested, furnished to:
- A subcontractor that is NOT registered with the DIR is listed on a bid for a public works project subject to prevailing wage. The likely consequence is that: