公共工程第 1585 / 1605 题

A contractor who pays workers LESS than the required prevailing wage on a public works project is subject to:

a.No consequence if the workers agree
b.Automatic loss of the contractor's home
c.Payment of back wages plus statutory penalties per worker per day of violation
d.A warning letter only

解析

Labor Code §1775 requires the contractor to pay the difference (back wages) to underpaid workers and imposes civil penalties for each calendar day each worker was paid less than the prevailing rate. Willful violations increase the penalties. Enforcement is by the Labor Commissioner.

法律依据: Labor Code §1775

免费刷完整 1605 道题库 — 无需注册。

同考点相关题目

最近核对: · 审核流程

Sen Lin, PrepPass 创始人 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen Licensed California General Contractor (CSLB License #1101856 核实)
反馈