公共工程第 1587 / 1632 题
Certified payroll records on a California public works project must generally be made available for inspection and, when requested, furnished to:
a.The project's design engineer and the awarding body's inspector
b.Any member of the public, in unredacted form, on demand
c.The DIR, the awarding body, and the Labor Commissioner
d.The county recorder, together with the notice of completion
解析
Labor Code §1776(b) makes certified payroll available for inspection and furnishes certified copies on request to the employee, to a representative of the body awarding the contract, and to the Division of Labor Standards Enforcement, which the Labor Commissioner heads inside the DIR. Designers and inspectors administer the work, not the payroll. The public may request records, but §1776(e) requires the worker's name, address and social security number to be obliterated first, so unredacted public access is wrong. The county recorder takes recorded notices; payroll is never filed there.
法律依据: Labor Code §1776(b)免费刷完整 1632 道题库 — 无需注册。
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
同考点相关题目
- Competitive bidding on public works generally requires the public agency to award the contract to the:
- A contractor who pays workers LESS than the required prevailing wage on a public works project is subject to:
- Which of the following is the BEST definition of 'public works' for prevailing wage purposes?
- A subcontractor that is NOT registered with the DIR is listed on a bid for a public works project subject to prevailing wage. The likely consequence is that:
- When a contractor must pay 'per diem wages' at the prevailing rate, this generally includes:
- On a public works project, a 'bid bond' submitted with a contractor's bid primarily guarantees that:
最近核对: · 审核流程
PrepPass 团队 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对