When a contractor must pay 'per diem wages' at the prevailing rate, this generally includes:

a.Only fringe benefits
b.Only the base hourly cash wage
c.The contractor's overhead and profit
d.The basic hourly rate PLUS employer payments for benefits such as health, pension, vacation, and training

解析

Prevailing 'per diem wages' (Labor Code §1773) include the basic hourly rate plus employer payments for fringe benefits — health and welfare, pension, vacation/holiday, and apprenticeship training contributions. Contractors must account for both the cash wage and the benefit components.

法律依据: Labor Code §1773