公共工程第 1589 / 1605 题
When a contractor must pay 'per diem wages' at the prevailing rate, this generally includes:
a.Only fringe benefits
b.Only the base hourly cash wage
c.The contractor's overhead and profit
d.The basic hourly rate PLUS employer payments for benefits such as health, pension, vacation, and training
解析
Prevailing 'per diem wages' (Labor Code §1773) include the basic hourly rate plus employer payments for fringe benefits — health and welfare, pension, vacation/holiday, and apprenticeship training contributions. Contractors must account for both the cash wage and the benefit components.
法律依据: Labor Code §1773免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- Which of the following is the BEST definition of 'public works' for prevailing wage purposes?
- Certified payroll records on a California public works project must generally be made available for inspection and, when requested, furnished to:
- A subcontractor that is NOT registered with the DIR is listed on a bid for a public works project subject to prevailing wage. The likely consequence is that:
- On a public works project, a 'bid bond' submitted with a contractor's bid primarily guarantees that:
- Failure to comply with apprenticeship requirements on a covered public works project can result in:
- 'Debarment' in the public works context means a contractor is: