保险与留置权第 1489 / 1605 题
An owner who learns that work is being done on their property without their authorization (e.g., by a tenant) can limit exposure to mechanics liens by recording and posting a:
a.Stop payment notice
b.Preliminary notice
c.Notice of completion
d.Notice of non-responsibility
解析
Civil Code §8444 (Notice of Non-Responsibility) lets an owner who did not cause the work and does not want to be responsible protect their interest by posting and recording the notice within 10 days of learning of the work. It is commonly used when a tenant orders improvements.
法律依据: Civ. Code §8170免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- An indemnity (hold-harmless) clause in a construction subcontract typically operates to:
- A recorded mechanics lien claim in California must include, among other things, a statement of the claimant's demand, the name of the owner, a description of the site, and:
- Under current California law, a mechanics lien is generally NOT enforceable unless the claimant:
- To be effective, a Notice of Non-Responsibility must generally be posted on the property and recorded within how many days after the owner obtains knowledge of the work of improvement?
- Which event does NOT constitute 'completion' of a work of improvement for purposes of starting mechanics lien deadlines on a private project?
- A 'notice of cessation' may be recorded by an owner when labor has ceased on the work of improvement for a continuous period of at least: