A 'notice of cessation' may be recorded by an owner when labor has ceased on the work of improvement for a continuous period of at least:
a.6 months
b.90 days
c.30 days
d.60 days
解析
Under Civil Code §8188, an owner may record a notice of cessation after labor has ceased for a continuous 30-day period. Recording it shortens the lien-recording deadlines for claimants (30 days for others, 60 for the direct contractor), similar to a notice of completion.
法律依据: Civ. Code §8188免费刷完整 1632 道题库 — 无需注册。
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
同考点相关题目
- An owner learns that a tenant has ordered work on the property without the owner's authorization. To limit exposure to mechanics liens, the owner records and posts:
- To be effective, a Notice of Non-Responsibility must generally be posted on the property and recorded within how many days after the owner obtains knowledge of the work of improvement?
- Which event does NOT constitute 'completion' of a work of improvement for purposes of starting mechanics lien deadlines on a private project?
- The party who purchases a surety bond and whose performance is guaranteed is called the:
- On a bond, the party who is protected and can make a claim if the principal defaults is the:
- An owner or contractor who wants to remove a recorded mechanics lien from title while still disputing the claim may record a:
最近核对: · 审核流程
PrepPass 团队 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — 核实)