保险与留置权第 1506 / 1632 题
A subcontractor asks to be added as an 'additional insured' on the general contractor's CGL policy. From a risk-management standpoint, this request is:
a.Prohibited, since a CGL policy may name only one insured entity
b.Standard, because every sub on a job is an insured under the prime's policy
c.Required, because the mechanics lien statute conditions lien rights on it
d.Backwards, since the upstream party is normally named on the sub's policy
解析
Risk flows upward in construction insurance: the owner and general contractor are named as additional insureds on the subcontractor's policy, so that liability arising from the sub's work is answered by the sub's insurer. A sub asking to be added to the prime's policy asks for the reverse. (a) is simply false — a CGL policy can carry many additional insureds by endorsement. (b) confuses being on the same job with being on the same policy. (c) is a category error; the mechanics lien statute says nothing about insurance.
免费刷完整 1632 道题库 — 无需注册。
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
同考点相关题目
- Commercial auto insurance for a contractor is primarily intended to cover:
- A claimant recorded a mechanics lien and did nothing further for four months. What is the status of the lien?
- A subcontractor recorded a mechanics lien but never served a copy on the owner and did not attach a proof of service affidavit. The likely result is:
- Which best describes who must carry workers' compensation insurance?
- Compared to a mechanics lien, a key ADVANTAGE of a stop payment notice for a lower-tier claimant is that it:
- A certificate of insurance shows a policy in force for a full year, but the insurer cancelled that policy the following week. The holder's coverage is:
最近核对: · 审核流程
PrepPass 团队 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — 核实)