A claimant recorded a mechanics lien and did nothing further for four months. What is the status of the lien?

a.It has become a judgment lien against the owner's property
b.It has expired, no action having been filed in 90 days
c.It remains enforceable for a year from the recording date
d.It has converted itself into a stop payment notice

解析

Civil Code §8460(a) requires the claimant to commence an action to enforce the lien within 90 days after the claim of lien is recorded, and provides that the lien otherwise expires and is unenforceable; four months is past the deadline. (c) uses a real figure from the wrong subdivision: §8460(b) extends the deadline only where the claimant and owner agreed to extend credit and recorded notice of it, and even then no later than one year after completion. (a) and (d) invent conversions the statute does not provide — a judgment lien needs a judgment, and a stop payment notice is a separate remedy that must be given while undisbursed funds remain.

法律依据: Civ. Code §8460(a)-(b)

免费刷完整 1632 道题库 — 无需注册。

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

同考点相关题目

最近核对: · 审核流程

PrepPass 团队 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — 核实)
反馈