A claimant recorded a mechanics lien and did nothing further for four months. What is the status of the lien?
解析
Civil Code §8460(a) requires the claimant to commence an action to enforce the lien within 90 days after the claim of lien is recorded, and provides that the lien otherwise expires and is unenforceable; four months is past the deadline. (c) uses a real figure from the wrong subdivision: §8460(b) extends the deadline only where the claimant and owner agreed to extend credit and recorded notice of it, and even then no later than one year after completion. (a) and (d) invent conversions the statute does not provide — a judgment lien needs a judgment, and a stop payment notice is a separate remedy that must be given while undisbursed funds remain.
法律依据: Civ. Code §8460(a)-(b)免费刷完整 1632 道题库 — 无需注册。
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
同考点相关题目
- A performance bond on a construction project primarily guarantees to the obligee that:
- Which of the following is generally NOT covered by a standard Commercial General Liability policy?
- Commercial auto insurance for a contractor is primarily intended to cover:
- A subcontractor recorded a mechanics lien but never served a copy on the owner and did not attach a proof of service affidavit. The likely result is:
- A subcontractor asks to be added as an 'additional insured' on the general contractor's CGL policy. From a risk-management standpoint, this request is:
- Which best describes who must carry workers' compensation insurance?
最近核对: · 审核流程