On a private remodel with no notice of completion recorded, the owner moves in and all labor stops. The 90-day lien clock runs from:
a.The date of the last progress payment
b.The date the building permit was issued
c.The date the construction contract was signed
d.Occupation by the owner with labor ceased
解析
Civil Code §8180(a) lists the completion events: actual completion; occupation or use by the owner accompanied by cessation of labor; cessation of labor for a continuous period of 60 days; and recordation of a notice of cessation after labor has stopped for 30 days. Here the second applies, and because no notice of completion was recorded, §8412 gives the direct contractor 90 days from completion and §8414 gives every other claimant 90 days from it. (a), (b) and (c) are all real dates in the project record, and none of them starts a lien clock — which is why a claimant who counts from the last payment or from signing records too late.
法律依据: Civ. Code §8180(a)(2) / §8412 / §8414免费刷完整 1632 道题库 — 无需注册。
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
同考点相关题目
- Which best describes who must carry workers' compensation insurance?
- Compared to a mechanics lien, a key ADVANTAGE of a stop payment notice for a lower-tier claimant is that it:
- A certificate of insurance shows a policy in force for a full year, but the insurer cancelled that policy the following week. The holder's coverage is:
- Why does an owner require the general contractor to furnish BOTH a performance bond and a payment bond?
- In a hold-harmless agreement, the 'indemnitor' is the party that:
- Why serve the preliminary notice at the start of a project, when payment is still arriving on time?
最近核对: · 审核流程
PrepPass 团队 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — 核实)