保险与留置权第 1513 / 1605 题

Best practice is to serve the Preliminary Notice at the START of a project even if payment is currently on time, because:

a.It automatically extends the lien deadline to one year
b.Late service limits lien and stop-notice rights to work furnished within 20 days before the notice; early service preserves the full claim
c.It is legally required to be served before signing any contract
d.It waives the need to record a lien later

解析

Because Civil Code §8204 limits recoverable amounts when notice is late, serving the preliminary notice within 20 days of first furnishing preserves lien and stop payment notice rights for the entire claim. Waiting risks losing rights for early work if a dispute later arises.

法律依据: Civ. Code §8200

免费刷完整 1605 道题库 — 无需注册。