保险与留置权第 1515 / 1605 题

A notice of completion was recorded on July 1. An unpaid drywall subcontractor wants to record a mechanics lien. The last day to record is approximately:

a.July 5
b.August 30 (60 days)
c.September 29 (90 days)
d.July 31 (30 days)

解析

Under Civil Code §8414, once a notice of completion is recorded, a claimant other than the direct contractor must record within 30 days. Counting 30 days from July 1 lands at the end of July. Only the direct contractor would get 60 days.

法律依据: Civ. Code §8414