A notice of completion was recorded on July 1. An unpaid drywall subcontractor wants to record a mechanics lien. The last day to record is approximately:
a.July 5
b.August 30 (60 days)
c.September 29 (90 days)
d.July 31 (30 days)
解析
Under Civil Code §8414, once a notice of completion is recorded, a claimant other than the direct contractor must record within 30 days. Counting 30 days from July 1 lands at the end of July. Only the direct contractor would get 60 days.
法律依据: Civ. Code §8414免费刷完整 1632 道题库 — 无需注册。
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
同考点相关题目
- In a hold-harmless agreement, the 'indemnitor' is the party that:
- Why serve the preliminary notice at the start of a project, when payment is still arriving on time?
- Which statement about surety bonds is TRUE?
- The 'your work' exclusion in a CGL policy means the policy generally will NOT pay to:
- A mechanics lien attaches to:
- Which document actually grants an owner additional insured status under the general contractor's liability policy?
最近核对: · 审核流程
PrepPass 团队 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — 核实)