After an owner records a lien release bond of 125%, an unpaid subcontractor who wants to be paid must now pursue:
a.The CSLB Recovery Fund
b.The surety on the release bond (and the principal), since the bond substitutes for the property
c.The construction lender's shareholders
d.The real property through foreclosure only
解析
When a lien release bond is recorded under Civil Code §8424, the bond substitutes for the property as security. The claimant's foreclosure remedy shifts to an action on the bond against the surety (and principal) rather than the real property.
法律依据: Civ. Code §8424免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- A subcontractor who is added as additional insured on NO ONE's policy and carries its own CGL is protected for third-party claims:
- The construction lender must be served with a preliminary notice by a claimant lacking an owner contract primarily so the claimant can later:
- On a public works project, subcontractors generally CANNOT record a mechanics lien against the public property. Their principal payment security instead is the:
- 'Employers' liability' coverage, usually part of a workers' compensation policy, protects the employer against:
- A direct contractor completed a private remodel on March 1. No notice of completion was ever recorded and the owner never occupied. The contractor's last day to record a mechanics lien is approximately:
- Requiring a subcontractor to provide a certificate of insurance BEFORE it starts work is a best practice primarily because it: