保险与留置权第 1560 / 1632 题
Requiring a subcontractor to provide a certificate of insurance BEFORE it starts work is a best practice primarily because it:
a.Makes the general contractor a policyholder from the first work day
b.Prevents the insurer from cancelling the policy during the project
c.Extends the general contractor's own coverage over the sub's work
d.Confirms the required coverage is in force before work starts
解析
Checking the certificate before the sub mobilizes verifies that the required coverage exists at the moment exposure begins, when it is still possible to keep an uninsured sub off the site. (a) confuses receiving a document with buying a policy. (b) reads the certificate as controlling the insurer, which it does not — cancellation rights live in the policy. (c) reverses the transfer: the purpose is to reach the sub's insurer for the sub's work, not to spend the general contractor's own limits on it.
免费刷完整 1632 道题库 — 无需注册。
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
同考点相关题目
- After an owner records a lien release bond of 125%, an unpaid subcontractor who wants to be paid must now pursue:
- 'Employers' liability' coverage, usually part of a workers' compensation policy, protects the employer against:
- A direct contractor completed a private remodel on March 1. No notice of completion was ever recorded and the owner never occupied. The contractor's last day to record a mechanics lien is approximately:
- Which best describes the difference between the payment bond and the performance bond on the SAME project?
- A mechanics lien recorded on a private project must describe the property with:
- 'Additional insured' status is most valuable to an upstream party (like an owner or GC) because it:
最近核对: · 审核流程
PrepPass 团队 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — 核实)