Requiring a subcontractor to provide a certificate of insurance BEFORE it starts work is a best practice primarily because it:
a.Makes the GC the policyholder
b.Extends the mechanics lien deadline
c.Guarantees the sub will never be canceled
d.Confirms required coverage is in force before the sub creates any exposure on the job
解析
Obtaining the certificate before work begins verifies the sub's required coverage is in place before any liability-creating work occurs. It is a front-end risk-management control, though the GC should also require additional insured endorsements for actual coverage.
免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- After an owner records a lien release bond of 125%, an unpaid subcontractor who wants to be paid must now pursue:
- 'Employers' liability' coverage, usually part of a workers' compensation policy, protects the employer against:
- A direct contractor completed a private remodel on March 1. No notice of completion was ever recorded and the owner never occupied. The contractor's last day to record a mechanics lien is approximately:
- Which best describes the difference between the payment bond and the performance bond on the SAME project?
- A mechanics lien on a private project should describe the property with:
- 'Additional insured' status is most valuable to an upstream party (like an owner or GC) because it: