A contractor begins demolishing a homeowner's bathroom before the written home improvement contract is signed. Under the Contractors State License Law, this is:

a.Permissible, as long as the contract is signed within 30 days
b.Permissible if the homeowner gave verbal approval
c.Permissible if the down payment was already paid
d.A violation, because the contract must be signed by both parties before work begins

解析

B&P §7159 requires that a home improvement contract be signed by both parties and a copy given to the owner before any work is performed. Starting work first is a violation.

法律依据: B&P §7159(a)