合同与履行第 722 / 1632 题

In addition to the contract price, a home improvement contract that includes a finance charge must separately disclose:

a.The dollar amount of the finance charge
b.The homeowner's credit score
c.The contractor's profit margin
d.The subcontractors' hourly rates

解析

B&P §7159 requires the contract to state the total contract price and, if financing is involved, to disclose the amount of any finance charge separately from the cash price.

法律依据: B&P §7159(c)