合同与履行第 724 / 1605 题

A homeowner calls a plumber for an urgent $400 leak repair. The plumber may use a service and repair contract only if, among other conditions, the plumber:

a.Adds a mandatory maintenance plan
b.Requires a 25% deposit
c.Extends the job to a full remodel
d.Does not sell or promote goods or services beyond what is reasonably necessary to complete the requested work

解析

B&P §7159.10 conditions the use of a service and repair contract on the contractor limiting the work to what the buyer requested and not upselling goods or services beyond what is reasonably necessary.

法律依据: B&P §7159.10