Which of the following must a home improvement contract include regarding the work to be done?

a.A description of the project and the significant materials and equipment
b.The total contract price, and nothing further about the work that will be done
c.The contractor's bank account details, so the owner can wire progress payments
d.The completion date alone, with the work described orally at the job site instead

解析

B&P §7159(d)(7) requires the heading 'Description of the Project and Description of the Significant Materials to be Used and Equipment to be Installed', followed by that description. It is what makes the scope enforceable and what any change order has to be measured against. (b) is the bare-price contract the statute exists to outlaw; the price is required too (§7159(d)(5)), but a price with no described scope is not a compliant contract. (d) leaves the scope oral, which is exactly what §7159(d) forbids. (c) is required nowhere and solves nothing: §7159.5(a)(5) bars accepting payment beyond the value in place, so a wire authorization is no substitute for a payment schedule.

法律依据: Bus. & Prof. Code §7159(d)(5), (7); §7159.5(a)(5)

免费刷完整 1632 道题库 — 无需注册。

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

同考点相关题目

最近核对: · 审核流程

PrepPass 团队 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — 核实)
反馈