合同与履行第 729 / 1605 题
On a $50,000 whole-house remodel, a contractor wants the largest lawful down payment. Without a joint control, that amount is:
a.$5,000
b.$1,000
c.$2,500
d.$500
解析
The cap is $1,000 or 10%, whichever is less. Ten percent of $50,000 is $5,000, but the $1,000 ceiling is lower, so the maximum lawful down payment is $1,000.
法律依据: B&P §7159(d)免费刷完整 1605 道题库 — 无需注册。