合同与履行第 733 / 1605 题

A contractor's payment schedule requires the owner to pay 80% of the price before any materials arrive or work begins. This violates §7159 because:

a.The owner must pay 100% up front
b.Payments may not exceed the value of work performed and materials delivered
c.Only cash payments are allowed
d.Payments must always be equal

解析

Front-loading payments so the owner pays far more than the value of completed work violates B&P §7159, which ties each payment to work actually performed and materials delivered.

法律依据: B&P §7159(d)