合同与履行第 733 / 1605 题
A contractor's payment schedule requires the owner to pay 80% of the price before any materials arrive or work begins. This violates §7159 because:
a.The owner must pay 100% up front
b.Payments may not exceed the value of work performed and materials delivered
c.Only cash payments are allowed
d.Payments must always be equal
解析
Front-loading payments so the owner pays far more than the value of completed work violates B&P §7159, which ties each payment to work actually performed and materials delivered.
法律依据: B&P §7159(d)免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- A home improvement contract is signed for $800. Does the written-contract requirement of §7159 apply?
- The three-day right to cancel a home improvement contract applies primarily to contracts that are:
- The 'Notice to Owner' that must accompany a home improvement contract primarily explains:
- Which scenario would DISQUALIFY a job from using the service and repair contract form?
- The required title 'Home Improvement' and the mandatory notices in a §7159 contract must be presented in a way that is:
- A home improvement contract must state the total price the buyer will pay, described as the: