合同与履行第 734 / 1605 题

Which scenario would DISQUALIFY a job from using the service and repair contract form?

a.The final price is $1,500 for the requested repair
b.The total is $600 and paid on completion
c.The homeowner phoned to request the repair
d.No down payment is collected

解析

A service and repair contract requires the price to be $750 or less. A $1,500 job exceeds that limit and must use a full home improvement contract.

法律依据: B&P §7159.10

免费刷完整 1605 道题库 — 无需注册。

同考点相关题目

最近核对: · 审核流程

Sen Lin, PrepPass 创始人 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen Licensed California General Contractor (CSLB License #1101856 核实)
反馈