合同与履行第 734 / 1632 题

Which scenario would DISQUALIFY a job from using the service and repair contract form?

a.The final price is $1,500 for the requested repair
b.The total is $600 and paid on completion
c.The homeowner phoned to request the repair
d.No down payment is collected

解析

A service and repair contract requires the price to be $750 or less. A $1,500 job exceeds that limit and must use a full home improvement contract.

法律依据: B&P §7159.10