合同与履行第 871 / 1632 题

The doctrine of 'impossibility' (or impracticability) may excuse performance when:

a.One party found a better opportunity somewhere else after the contract was signed
b.The contractor underestimated the cost of labor at the time he prepared the bid
c.The work turned out to be a good deal less profitable than the contractor expected
d.An unforeseen event, through no party's fault, prevents performance entirely

解析

Civil Code §1511 excuses performance prevented or delayed by an irresistible superhuman cause, by the operation of law, or by the other party, and the courts add commercial impracticability — extreme and unreasonable difficulty or expense that was not foreseeable, not merely more than was budgeted. The three distractors are one error in three costumes. (b) is estimating risk, which is precisely what a fixed price allocates to the contractor. (c) is reduced profit, which the doctrine has never covered. (a) is opportunity cost, not an excuse at all but a reason for a breach the contractor still pays for. Compare frustration of purpose, where performance stays entirely possible but the shared reason for it is gone.

法律依据: Civil Code §1511

免费刷完整 1632 道题库 — 无需注册。

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

同考点相关题目

最近核对: · 审核流程

PrepPass 团队 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — 核实)
反馈