合同与履行第 872 / 1632 题

'Frustration of purpose' as an excuse for nonperformance applies when:

a.An unforeseen event destroys the shared purpose, although performance still remains possible
b.An unforeseen event destroys the subject matter itself, making performance physically impossible
c.An unforeseen event makes performance far costlier than either of the parties had ever expected
d.One party simply finds the bargain a good deal less attractive than it had originally hoped for

解析

Frustration of purpose excuses performance when an event neither party foresaw destroys the principal purpose both understood as the basis of the bargain, even though the promised performance remains entirely possible — the textbook case is renting a room to watch a parade that is then cancelled. (b) is impossibility, where performance itself cannot be rendered; the doctrines are neighbours, not synonyms, and Civil Code §1511 sets out when performance is excused. (c) is commercial impracticability, which California applies narrowly: added cost, even large added cost, is the risk a fixed-price contractor accepted. (d) is buyer's remorse, which excuses nothing at all.

法律依据: Civil Code §1511

免费刷完整 1632 道题库 — 无需注册。

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

同考点相关题目

最近核对: · 审核流程

PrepPass 团队 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — 核实)
反馈