合同与履行第 877 / 1605 题

A general contractor uses a subcontractor's bid to prepare and win the prime contract, reasonably relying on that bid. If the sub then tries to withdraw the bid, the general may argue the sub is bound under:

a.The parol evidence rule
b.Promissory estoppel, based on the general's reasonable reliance on the sub's bid
c.The Statute of Frauds only
d.A force majeure clause

解析

Courts have applied promissory estoppel to hold a subcontractor to its bid when a general contractor reasonably and foreseeably relies on that bid in preparing and submitting its own successful prime bid. The sub should expect such reliance, and injustice would result if the sub could freely withdraw after the general is committed. The parol evidence rule, the Statute of Frauds, and force majeure clauses do not address this reliance-based enforcement of a bid.

免费刷完整 1605 道题库 — 无需注册。

同考点相关题目

最近核对: · 审核流程

Sen Lin, PrepPass 创始人 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen Licensed California General Contractor (CSLB License #1101856 核实)
反馈