A general contractor uses a subcontractor's bid to prepare and win the prime contract, reasonably relying on that bid. If the sub then tries to withdraw the bid, the general may argue the sub is bound under:
解析
Drennan v. Star Paving Co. (1958) 51 Cal.2d 409 is the California authority: a subcontractor who submits a bid knowing the general will use it in a prime bid should expect reliance, and once the general wins the job on the strength of that number the sub's offer becomes irrevocable for a reasonable time. No consideration was paid to hold the bid open; reliance takes its place. (a) inverts the parol evidence rule, which excludes outside evidence contradicting an integrated writing — it cannot make an offer binding. (c) treats the writing as the source of the obligation; the Statute of Frauds says which agreements need a writing, and a signed bid is still only an offer until accepted. (d) is a clause for events beyond a party's control; changing one's mind about a price is not such an event.
法律依据: Drennan v. Star Paving Co. (1958) 51 Cal.2d 409免费刷完整 1632 道题库 — 无需注册。
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
同考点相关题目
- An 'incidental beneficiary' of a contract differs from an intended beneficiary in that an incidental beneficiary:
- A contractor's bid submitted to an owner is best characterized in contract terms as:
- 'Promissory estoppel' may allow enforcement of a promise, even without traditional consideration, when:
- A 'retention' (retainage) provision in a construction contract generally allows the owner to:
- A 'progress payment' schedule in a construction contract is designed to:
- A contract that is unfair and one-sided to the point of shocking the conscience, formed under grossly unequal bargaining power, may be held unenforceable as:
最近核对: · 审核流程