合同与履行第 878 / 1632 题

A 'retention' (retainage) provision in a construction contract generally allows the owner to:

a.Take ownership of the contractor's tools until completion
b.Charge the contractor a fee for administering payments
c.Withhold part of each payment until work is accepted
d.Delay paying for completed work until the warranty expires

解析

A retention or retainage clause lets the owner withhold part of each progress payment as security that the contractor will finish properly and correct defects, releasing it after satisfactory completion or acceptance (c). The percentage is no longer open-ended: Public Contract Code §7201 caps most public works at 5%, and Civil Code §8811 caps private works at 5% for contracts entered into on or after January 1, 2026, leaving the older 10% practice only for pre-2026 contracts and the statute's narrow exceptions. (a) is wrong because retention is money held back, not a claim on the contractor's property. (b) confuses retention with an administrative charge — retention is the contractor's own earned money, held temporarily, not a fee. (d) is wrong because the withheld money is paid when the conditions are met; a warranty period does not license the owner to keep deferring it.

免费刷完整 1632 道题库 — 无需注册。

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

同考点相关题目

最近核对: · 审核流程

PrepPass 团队 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — 核实)
反馈