商业财务第 1227 / 1605 题
A contractor's job took 220 labor hours at a burdened rate of $48/hour. Materials were $9,400 and a sub billed $6,200. What was the total direct cost?
a.$10,560
b.$26,160
c.$21,160
d.$15,600
解析
Labor = 220 x $48 = $10,560. Direct cost = labor $10,560 + materials $9,400 + sub $6,200 = $26,160.
免费刷完整 1605 道题库 — 无需注册。
同考点相关题目
- A contractor records a $50,000 equipment purchase. On the balance sheet this transaction:
- A contractor wants to know the profit built into a bid before overhead. That figure is the:
- A homeowner's $30,000 remodel contract allows a 10% down payment maximum under home improvement rules. But 10% is $3,000, which exceeds the $1,000 cap. The lawful maximum down payment is:
- If a contractor's actual overhead runs 22% of direct costs but he only marks up 15% for overhead, over a year of $500,000 direct costs he under-recovers roughly:
- A balance sheet is said to 'balance' because:
- A contractor factors (sells) $50,000 of receivables to a factor who advances 90% now and charges a 3% fee on the face amount. How much cash does the contractor receive up front, and what is the fee?