商业财务第 1228 / 1632 题

If a contractor's actual overhead runs 22% of direct costs but he only marks up 15% for overhead, over a year of $500,000 direct costs he under-recovers roughly:

a.$110,000
b.$35,000
c.$7,500
d.$75,000

解析

Under-recovery rate = 22% - 15% = 7% of direct costs. 7% x $500,000 = $35,000 of overhead not recovered through pricing, which comes straight out of profit. Accurate overhead rates are critical.

免费刷完整 1632 道题库 — 无需注册。

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

同考点相关题目

最近核对: · 审核流程

PrepPass 团队 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — 核实)
反馈