商业财务第 1132 / 1632 题

Poor cash flow on a construction project is MOST often caused by:

a.Paying suppliers early to take their discount
b.Holding retention back from all the subcontractors
c.Billing the owner monthly rather than weekly
d.Paying labour and materials before billings land

解析

The structural cause is timing: wages and material invoices fall due weeks before the owner pays a progress billing, and retention delays part of the receipt further still, so cash drains even on a profitable job. Taking an early-payment discount does consume cash, but it buys a return and is a choice rather than the cause. Monthly billing lengthens the gap and makes the problem worse, without being its origin. Withholding retention from subs conserves the contractor's cash rather than draining it.

免费刷完整 1632 道题库 — 无需注册。

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

同考点相关题目

最近核对: · 审核流程

PrepPass 团队 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — 核实)