A cash flow projection primarily helps a contractor:
a.Foresee cash shortfalls in time to arrange credit
b.Set the overhead rate each bid should carry
c.Value the work in progress for the balance sheet
d.Compute the depreciation on owned equipment
解析
A cash flow projection lays expected receipts against expected disbursements week by week, so a shortfall is visible before it arrives and a line of credit or a change in billing can be arranged in time. Markup comes from the overhead rate and the target margin, not from a cash schedule. Work in progress is valued from job-cost records against the contract amounts. Depreciation follows the asset's cost and schedule and is a tax and book calculation, with no cash timing in it at all.
免费刷完整 1632 道题库 — 无需注册。
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
同考点相关题目
- Poor cash flow on a construction project is MOST often caused by:
- Why can a contractor be profitable on paper yet still run out of cash?
- A contractor offers 2/10, net 30 terms and pays a $10,000 supplier invoice on day 8. How much does he pay?
- The current ratio is calculated as:
- A contractor has current assets of $200,000 and current liabilities of $80,000. What is his current ratio?
- Which financial statement reports a company's assets, liabilities, and owner's equity at a single point in time?
最近核对: · 审核流程
PrepPass 团队 · 依据官方资料核对 California CSLB Contractor License Law & Business Exam · 我们如何核对
审核人 Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — 核实)